New federal report critical of Hanford nuke waste plant work

RICHLAND, Wash. (AP) - A strongly worded new report from a congressional watchdog agency questions whether an often-delayed and increasingly expensive waste treatment plant at the nation's most contaminated nuclear site can be built and operated successfully.
Released Friday, the report by the Government Accountability Office criticizes the U.S. Department of Energy and those building the plant for their performance during construction of the facility at the Hanford nuclear reservation in south-central Washington.
The Oregonian reports that the analysis was prepared at the request of congressional leaders.
"By just about any definition, DOE's (waste treatment plant) project at Hanford has not been a well-planned, well-managed, or well-executed major capital construction project," the GAO report said.
"Daunting technical challenges that will take significant effort and years to resolve, combined with a near tripling of project costs and a decade of schedule delays, raise troubling questions as to whether this project can be constructed and operated successfully."
Earlier this week, Washington state and federal officials said construction can begin to be ramped up again. That word came nearly seven months after a new cost estimate and construction schedule were delayed to address technical problems and safety concerns.
Design of the $12.3 billion plant is 85 percent complete while construction is more than 50 percent complete.
The plant has long been considered the cornerstone of cleanup at Hanford. However, the Energy Department, which manages cleanup at the site, halted construction on significant portions of the plant amid technical issues and concerns about its eventual safe operation.
Then-Gov. Chris Gregoire and Energy Secretary Steven Chu said in a statement Tuesday that the state and federal government have worked closely to resolve those issues in recent months and that, based on information gathered from leading scientific experts, the Energy Department is confident that construction can be ramped back up again.
The federal government created Hanford in the 1940s as part of the top-secret Manhattan Project to build the atomic bomb.
The plant will convert millions of gallons of highly radioactive waste into glasslike logs for permanent storage. That waste is currently stored in 177 aging, underground tanks, many of which have leaked into the groundwater, threatening the neighboring Columbia River.
The plant's design includes new technology that will need to operate for decades "with perfect reliability," the GAO report said, because high radiation levels won't allow access for maintenance and repair.
The Oregonian reports that the GAO recommended against resuming construction until key milestones are met, including verifying critical technologies.
Responding to the report, the Energy Department said it would allow limited construction, such as completing structural walls at the high-level treatment plant, while "taking into account the remaining open technical issues."
The accountability office said that approach "appears reasonable," the newspaper reported.
DOE also said it would work to improve contractor performance evaluations, and would review incentive payments made since January 2009.
Released Friday, the report by the Government Accountability Office criticizes the U.S. Department of Energy and those building the plant for their performance during construction of the facility at the Hanford nuclear reservation in south-central Washington.
The Oregonian reports that the analysis was prepared at the request of congressional leaders.
"By just about any definition, DOE's (waste treatment plant) project at Hanford has not been a well-planned, well-managed, or well-executed major capital construction project," the GAO report said.
"Daunting technical challenges that will take significant effort and years to resolve, combined with a near tripling of project costs and a decade of schedule delays, raise troubling questions as to whether this project can be constructed and operated successfully."
Earlier this week, Washington state and federal officials said construction can begin to be ramped up again. That word came nearly seven months after a new cost estimate and construction schedule were delayed to address technical problems and safety concerns.
Design of the $12.3 billion plant is 85 percent complete while construction is more than 50 percent complete.
The plant has long been considered the cornerstone of cleanup at Hanford. However, the Energy Department, which manages cleanup at the site, halted construction on significant portions of the plant amid technical issues and concerns about its eventual safe operation.
Then-Gov. Chris Gregoire and Energy Secretary Steven Chu said in a statement Tuesday that the state and federal government have worked closely to resolve those issues in recent months and that, based on information gathered from leading scientific experts, the Energy Department is confident that construction can be ramped back up again.
The federal government created Hanford in the 1940s as part of the top-secret Manhattan Project to build the atomic bomb.
The plant will convert millions of gallons of highly radioactive waste into glasslike logs for permanent storage. That waste is currently stored in 177 aging, underground tanks, many of which have leaked into the groundwater, threatening the neighboring Columbia River.
The plant's design includes new technology that will need to operate for decades "with perfect reliability," the GAO report said, because high radiation levels won't allow access for maintenance and repair.
The Oregonian reports that the GAO recommended against resuming construction until key milestones are met, including verifying critical technologies.
Responding to the report, the Energy Department said it would allow limited construction, such as completing structural walls at the high-level treatment plant, while "taking into account the remaining open technical issues."
The accountability office said that approach "appears reasonable," the newspaper reported.
DOE also said it would work to improve contractor performance evaluations, and would review incentive payments made since January 2009.
At this rate it will never get cleaned up. Meanwhile, the Columbia River and surrounding ground water gets more and more contaminated. I don't think they really know what's going on down there. Terrible side effect of our need for power but as history has shown we seem to hit the wall before we see many of our mistakes. The worst part is that future generations will have a much bigger price to pay than those of us who will be long gone.
What form is the highly radioactive waste in.... as it sits now?
Â
Maybe these "converted glass-like logs" could just be stored in those shiny new 520 floating bridge pontoons?
Â
Nuclear Reactors are looked at as a "horrible source of energy", however, the by-product from those reactors are very beneficial to Nuclear Medicine. Medical diagnostics are so successful finding health ailments by using very minute amout of radioactivity. Many lives have been saved by the use of radiopharmaceuticals. Also, nuclear energy is clean to the enviroment, the issues become with the engineering of some reactors (i.e. Japan Reactor). Other than that, Reactors are relatively safe with great benefits.
Its never going to work anyways. First mechanical problem and its done. Time to restructure all nuclear facilities to use thorium instead. A lot safer. Its either that or its time to just shutdown all these nuclear reactors.
@Blindman Why Thorium? It has a half life of 14 billion years and is an alpha emitter. It is also a non-fissel isotope, meaning that it cannot be used for a nuclear reactor without another "driver" isotope, which is usually Uranium or Plutonium. So, although Thorium would be a nice alternative, it does not have the energy to drive a Nuclear Reactor.
Â
@Eye4anEye Thank you for the FYI.
@Blindman what is thorium? and why is that safer?
you know they would have been done 10 years ago if they would stop this ramp up ramp down change this change that. go back to that. No change it again. Some people I know who have worked on that. have built the same things over 100 times. complete boondoggle